Forum

Ambiguity in Financial Obligations in Commercial Contracts

Auteur Message

swiftc
Date d'envoi: 11/09/2024 13:33:37
Ambiguity in financial obligations is common in commercial contracts, where clarity or imprecise terms can lead to disputes between parties. In this case, the focus is on how such ambiguity affects a construction contract in Malaysia and the legal strategies for resolving the conflict.

Dispute Over Ambiguous Payment Terms in a Construction Contract

Client Overview: A Malaysian construction company contracts with a property developer to build a commercial complex. The agreement contains vague payment terms regarding the timing of progress payments and penalties for late payment. Midway through the project, the construction company faces delays in receiving payments from the developer, leading to cash flow issues and project delays. The developer claims that the contract did not clearly define the payment schedule.

Identifying Ambiguity in the Contract
Ambiguous Clauses: The payment clause in the contract states that "progress payments shall be made promptly upon the completion of each phase of the project," but it does not define:

- What constitutes "completion" of a phase,
- The timeline for "prompt" payment,
- Specific dates or triggers for payments or
- Penalties for late payments.
This lack of clarity creates ambiguity in financial obligations and opens the door to disputes.

Consequences of Ambiguity in Financial Obligations
a. Project Delays and Cash Flow Issues
The construction company experiences cash flow problems because the developer delays payments, claiming the project phases were not "fully completed" according to its contract interpretation. The delay in payments leads to slowdowns in procurement of materials and labour, further delaying the project timeline.

b. Legal Disputes
The ambiguity in the payment terms leads to disagreements about when payments should be made. The construction company argues that payment is due when each phase reaches substantial completion. At the same time, the developer claims payments are only due upon final certification by an independent surveyor.

Example: In a similar case, a Malaysian court found that the phrase "prompt payment" in a contract was too vague and required further interpretation. As a result, the court had to look into extrinsic evidence such as emails, negotiations, and industry standards to determine what the parties originally intended.

Legal Remedies and Resolution Strategies
a. Contractual Interpretation
Role of Courts: If the dispute escalates to court, the judge will seek to interpret the ambiguous clauses in line with the Contracts Act 1950. Malaysian courts typically adopt a purposive approach, meaning they will try to determine the actual intent of the parties at the time of contracting based on the following:

- The overall contract structure and context,
- Pre-contract negotiations and correspondences, and
- Industry practices in construction payment schedules.

Case Reference: In a case involving construction disputes (e.g., Tri-Pacific Engineering & Construction Co. v. Tenaga Nasional Berhad), the Malaysian courts ruled that where ambiguity exists, the interpretation that makes the contract workable for both parties should be adopted. This reinforces the need for a clear, operational definition of contract financial obligations.





Retour au site